Â鶹´«Ã½

2/11- Cunningham Hall Renovation Updates

Work in progress:

  • Completed AHU #3 duct tie-in to AHU #2.
  • Air handler unit #3 has been permanently shutdown.
  • Start layout for tele/data ductbanks.
  • Starting motor control center (MCC) and swithgear duct bank.
  • Started mass excavation - currently 95% complete.  Shoring and lagging is now complete.
  • Installing exterior scaffolding to 3rd floor on the west side of the building inside the construction fence.
  • Phoenix air valve replacement in the Annex research labs continues per schedule.

Looking ahead for next week:

  • Start demolition of AHU #3.
  • Continue chilled water piping in 3rd floor east mechanical room.
  • Complete the 10" water line relocation.
  • Continue abatement of 3rd floor west mechanical room.
  • Start prep work for abatement in 3rd floor east mechanical room.
  • Start electrical service from MCC to new AHU #1 in the 3rd floor east mechanical room.
  • Continue Phoenix air valve replacement in the Annex.
POSTED: Thursday, February 11, 2016 05:43 PM
Updated: Saturday, December 3, 2022 01:02 AM