Â鶹´«Ã½

2/11- ISB Construction Updates

Work in progress:

  • Site shoring around the building is complete - contractor is demobilizing.
  • 130 Piles are complete on the north end of the site (approximately to column line 7).
  • Temporary ramp into excavation is complete.
  • Sanitary tie-in on the north side has been completed.
  • Pile caps and grade breams have begun.
  • Mass excavation is complete.

Looking ahead:

  • Remove fencing around the sanitary tie-in location on the North side of the site.  This will reopen a sidewalk to Williams Hall north entrance.
  • Installation of formwork for retaining wall will begin 2/15/2016.
  • Continue with pile caps and grade beams.
  • Continue with auger cast pile installation.
POSTED: Thursday, February 11, 2016 05:40 PM
Updated: Thursday, January 19, 2017 09:05 AM