Â鶹´«Ã½

2/4- Cunningham Hall Renovation Updates

Work in Progress:

  • Continuing the installation of the temporary duct and assembly of new AHU1 in the East side mechanical room.
  • Stripped topsoil from addition footprint.
  • Phoenix air valve replacement in the Annex research labs continues per schedule.
  • Continue coordination of the west mechanical room abatement and planning for demolition of AHU 3.
  • Excavated existing 10" water main that will be relocated for addition.
  • Fabricating duct for cross connect of AHU 2 & AHU 3.
  • Completed demolition of basement electrical room.

Looking ahead for next week:

  • Continue with mass excavation and shoring installation.
  • Shut down AHU 1 (East Side Mechanical Room) on 2/12 from 7:00pm thru Sunday 2/14 afternoon.  This unit supplies air the the east side of the building.
  • 2/9 Shut down AHU 2 between 6:00am - 7:00am to start cross connect between AHU 2 and AHU 3
  • 2/10 Shut down AHU 3 between 6:00am - 7:00am to complete the cross connect between AHU 2 and AHU 3
  • 2/11 Permanently shutdown AHU 3 and start demolition.
  • Continue Phoenix air valve replacement in the Annex.
  • Complete 10" water main relocation.
POSTED: Monday, February 8, 2016 09:32 AM
Updated: Saturday, December 3, 2022 01:02 AM