Â鶹´«Ã½

3/11- Smith Hall Renovation Update

Work in Progress:

  • Continuing the wall framing and electrical rough-in in room 101, 104, & 223.
  • Wall framing, electrical & plumbing rough-in continue in the new first floor restrooms.
  • Electrical floor box layout and core drilling has begun in 223.
  • Continuing the wall patch and repair in rooms with removed HVAC (Uni-vent) perimeter wall equipment.

Looking forward:

  • Start HVAC sheet metal ductwork on the first floor.
  • Planned power outage on 3/19/2016 to make connections to new switchgear.
  • Continue with sanitary and water rough-in in restrooms on the first floor.
  • Complete framing and rough-in for inspections prior to drywall boarding.
  • Continue with wall patching at HVAC (Uni-vent) demolition areas.
  • Demolition of 3rd floor relief air dampers scheduled for spring break.
  • Begin steel lift plan and layout work.
POSTED: Friday, March 11, 2016 12:00 AM
Updated: Saturday, December 3, 2022 01:02 AM