Â鶹´«Ã½

4/28- ISB Construction Updates

Work in Progress:

  • Forming basement retaining wall from column line 13G to 17C in progress.
  • Forming of lift #2 at elevator #2 (south) for second pour is in progress.
  • Forming of stair #3 is in progress.
  • Concrete piers along column line B are in progress.
  • Steel erection of sequence 1 - 4 are in progress.
  • Steel detailing of sequence 1 is in progress.
  • Williams Hall tunnel work has started with the temporary steam condensate line installation.

Looking forward:

  • Continue erection of steel sequences 1 - 4.
  • Continue with detailing steel sequence 1.
  • Pour elevator #2 lift #2 on 4/29.
  • Pour stair #3 lift #2 on the week of 5/2.
  • Pour basement retaining wall concrete from 13G to 17C.
  • Start forming retaining wall along column line 17B to 17C.
  • Continue work in tunnel in preparation for steam shutdown week.
  • Start chilled water line installation in Williams mechanical room for service to ISB.
POSTED: Thursday, April 28, 2016 12:00 AM
Updated: Thursday, January 19, 2017 09:05 AM