Â鶹´«Ã½

4/28- Smith Hall Renovation Updates

Work in Progress:

  • Fire alarm raceways are approximately 75% complete.
  • Electric Panel 1J is complete.
  • HVAC duct installation continues on floor 2 and 3.
  • Temporary heaters have been removed from the building.
  • HVAC curb delivered and set on 4/27.
  • Door frame installation and drywall finishing happening throughout the building.

Looking forward:

  • AHU Air House delivery scheduled for delivery on week of 5/16.
  • New masonry opening to be cut-in on first floor.
  • Fire alarm wire will be pulled to device locations.
  • Remaining demolition and floor tile abatement will take place the week of 5/2.
  • Complete plumbing in restrooms.
  • Drywall taping and finishing throughout.
POSTED: Thursday, April 28, 2016 12:00 AM
Updated: Thursday, January 19, 2017 09:05 AM