Â鶹´«Ã½

5/12- ISB/Williams Hall Construction Updates

Work in Progress:

  • Forming at stair #3 for 3rd lift continues; 2nd lift pour has been completed.
  • Concrete piers along column line 'B' were completed.
  • Steel erection in sequence 1 - 4 continues.
  • Steel detailing in sequence 2 continues.
  • Basement retaining wall between column line 17/A.1 to 17/C in progress.
  • Steam, steam condensate and chilled water piping work in tunnel is in progress.
  • Removal of temporary overhead protection at Williams Hall dock area.
  • Chilled water line installation in Williams Hall mechanical room continues.

Looking forward:

  • Start installation on steel sequence #5 & #6.
  • Continue steel sequence #3 detailing.
  • Continue work at elevator #2 for 3rd concrete pour.
  • Complete forming for 3rd concrete pour next week.
  • Continue utility work in tunnels.
POSTED: Tuesday, May 12, 2015 12:00 AM
Updated: Saturday, December 3, 2022 01:02 AM