Year of Science
Â鶹´«Ă˝ College of Arts and Sciences is celebrating a Year of Science!
Â鶹´«Ă˝ will host the annual international conference of the Institute for Complex Adaptive Matter on May 16-18 at the Â鶹´«Ă˝ Hotel and Conference Center.
KENT STATE TO HOST ICAM/I2CAM CONFERENCE MAY 16-18
Â鶹´«Ă˝ will host the annual international conference of the Institute for Complex Adaptive Matter on May 16-18 at the Â鶹´«Ă˝ Hotel and Conference Center.Work in Progress:
Pulling wire throughout for branch circuits.
Installing duct on 1st floor.
Complete domestic water rough-in on the 2nd floor.
Sanitary piping rough-in has been completed on the 3rd floor.
Completing remaining framing throughout.
Starting door frame…
4/7- Smith Hall Renovation Updates
Work in Progress: Pulling wire throughout for branch circuits. Installing duct on 1st floor. Complete domestic water rough-in on the 2nd floor. Sanitary piping rough-in has been completed on the 3rd floor. Completing remaining framing throughout. Starting door frame…Work in Progress:
Forming lift 3 on elevator #1.
Working on retaining wall progressing south to column line A7.
Pile caps and foundations for elevator #2 are complete.
Looking forward:
Pour lift #3 on elevator #1 on 4/8/2016.
Steel delivery and erection begins for…
4/7- ISB/Williams Hall Construction Updates
Work in Progress: Forming lift 3 on elevator #1. Working on retaining wall progressing south to column line A7. Pile caps and foundations for elevator #2 are complete. Looking forward: Pour lift #3 on elevator #1 on 4/8/2016. Steel delivery and erection begins for…Â鶹´«Ă˝â€™s fourth annual Neuroscience Symposium will cover the latest research findings on “The Neuroscience of The Social Brain” on April 7-8 at the Â鶹´«Ă˝ Hotel and Conference Center located in downtown Kent, Ohio.
Kent State Holds Symposium on “The Neuroscience of the Social Brain” on April 7-8
Â鶹´«Ă˝â€™s fourth annual Neuroscience Symposium will cover the latest research findings on “The Neuroscience of The Social Brain” on April 7-8 at the Â鶹´«Ă˝ Hotel and Conference Center located in downtown Kent, Ohio.Image
Theresa Benyo already had an exciting and fulfilling career as a project manager at NASA. With a great job, a house, a husband, two kids, and hobbies like musical theatre what more could you want? Academically speaking, she’d already earned a dual bachelor’s degree in physics…
Becoming a Rocket Scientist
Theresa Benyo already had an exciting and fulfilling career as a project manager at NASA. With a great job, a house, a husband, two kids, and hobbies like musical theatre what more could you want? Academically speaking, she’d already earned a dual bachelor’s degree in physics…Work in Progress:
Working on pile caps and grade beams. Plan to start column line 17 (Southern most column line) next week.
Started working on forming elevator #2 (South).
Pouring elevator #1 second lift (North) today.
Continuing the installation of the basement…
3/24- Williams Hall/ISB Construction Updates
Work in Progress: Working on pile caps and grade beams. Plan to start column line 17 (Southern most column line) next week. Started working on forming elevator #2 (South). Pouring elevator #1 second lift (North) today. Continuing the installation of the basement…Work in Progress:
First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun.
Room 101 & 104 electrical rough-in is at 90% complete.
Machine Shop electric panel installed and completed on Saturday 3/19.
Room 223 electrical…
3/24- Smith Hall Renovation Updates
Work in Progress: First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun. Room 101 & 104 electrical rough-in is at 90% complete. Machine Shop electric panel installed and completed on Saturday 3/19. Room 223 electrical…Work in Progress:
Steam piping in the 3rd floor east mechanical room is 20% complete.
Steam condensate lines for the steam station and AHU#1 are in progress.
Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has…
3/24- Cunningham Hall Renovation Updates
Work in Progress: Steam piping in the 3rd floor east mechanical room is 20% complete. Steam condensate lines for the steam station and AHU#1 are in progress. Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has…Senior Research Fellow Quan Li, Ph.D., and his research group at Â鶹´«Ă˝â€™s Liquid Crystal Institute®, in the College of Arts and Sciences, have published a research article in the March 17 issue of Nature that could lead to a variety of breakthrough device…
Kent State Researchers Publish Breakthrough in Leading Scientific Journal
Senior Research Fellow Quan Li, Ph.D., and his research group at Â鶹´«Ă˝â€™s Liquid Crystal Institute®, in the College of Arts and Sciences, have published a research article in the March 17 issue of Nature that could lead to a variety of breakthrough device…Work in Progress:
Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18. Will be ready for cooling system startup on 4/15.
Currently insulating the chilled water pipes in the 3rd floor wast mechanical room.
Steam reducing station…